Dear Experts
We are facing an issue when we performing PGI on Consignment Fill order
Scenario is as follows
1) Material master maintained with no price or with a minimal price and standard cost estimate will not be done as it is variant configurable material ( lets assume material master maintained with 1 rupee as a standard price )
2) Consignment fill order created and sale order costing also completed ( assume EK02 updated with 10000 INR )
3) Production order created ( Goods Issue, confirmation , Goods receipts done )
4) On Performing Goods Receipts stock updated as sale order stock ( E Stock )
6) At this movement sale order stock values is 10000 INR
7) Performed PGI ( Delivery ) on consignment fill order
Expected result : sale order stock ( E ) Should be reduced with 10000 INR and customer consignment stock to be update with 10000 INR . that means stock should transfer from sale order stock to customer consignment stock with the same value
But actually what happening is that customer consignemnt stock is getting updated with mateiral master price i.e 1. that means sale order stock ( 631 E ) is reducing with 10000 inr and customer consignment stock ( 631 W ) is updating with 1 rupee and the difference between these two positng to expense on stock transfer which is not correct
So could you please advice , what are setting to be done to transfer the material from sale order stock ( 631 E ) to cusotmer consignement stock ( 631 W ) with same value , do we need to perform any specific settings in the system and what are configuation changes required for this
could you please explain in step by step
Regards
Gupta