Dear Experts
In my business scenario we have 7 different companies with different manufacturing process
we have finalized to capture the below overhead through the activity type among the group
Machine Hour
Setup hour
Maintance hour
Each and every company rates are different here my doubt is
- 1.Shall I have the Activity types company wise or common activites
2The activity type unit of measurement is HR, suppose if I do the production confirmation as MIN future am I going to face any problem
Could you please give your inputs
Thanks & Regards